Bond Election

  • January 23, 2017 - Board approved developing a Long-Range Facilities Planning Committee

    March 27, 2017 - Board approved Long-Range Facilities Planning Committee members

    August 7, 2017 - Board discussed Long-Range Faciliites Planning Committee recommendations

    August 10, 2017 - Board calls for $240 million Bond Election

    November 17, 2017 - Board canvassed Bond Election returns

Bond Approvals

  • March 30, 2015 - Board approved architectural firms 

    October 17, 2016 - Board approved reimbursement resolution

    December 18, 2017 - Board approved Construction delivery method

    December 18, 2017 - Board approved Local Emergency Planning Committee (tornado shelter)

    May 21, 2018 - Board approved job order contract renewal

    June 18, 2018 - Board approved Local Emergency Planning Committee 

    October 15, 2018 - Board approved Job Order Contract results and recommendations

    May 20, 2019 - Board approved Order Authorizing Issuance of Bonds per 2017 Bond Election Passing Proposition B

    June 17, 2019 - Board approved Lobo Lane Conversion Study

Bond Issuance

  • February 19, 2018 - Board approved $150 million Bond issuance

    June 18, 2018 - Board approved $25 million Bond issuance

Land Purchases

  • October 19, 2017 - Board approved letter of intent for land with Tribute Partners

    March 26, 2018 - Board approved 26.123 acres land purchase in Tribute at The Colony

    August 20, 2018 - Board approved 12.332 acres land purchase in Little Elm - Valencia L.P.

    August 20, 2018 - Board approved 1.177 acres land purchase in Little Elm - Hart Road

    August 26, 2018 - Board approved 35.24 acres land purchase in Oak Point - Wildridge L.L.P.

Bond Projects

  • Brent & Chavez Vestibule 
    May 21, 2018 - Board approved JOC and budget for Security Vestibules at Chavez Elementary School and Brent Elementary School 

    Walker Middle School
    April 23, 2018 - Board names the two middle schools 

    May 21, 2018 - Board approved construction manager for Walker Middle School

    October 15, 2018 - Board approved funding agreement for natural gas line extension at Walker Middle School and Transportation Facility

    December 17, 2018 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Walker Middle School

    Strike Middle School
    April 23, 2018 - Board names the two middle schools 

    May 21, 2018 - Board approved construction manager for Strike Middle School

    December 17, 2018 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Strike Middle School

    February 18, 2019 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Scotty's Lake Lane Off-Site Improvements

    Little Elm High School Ball Fields and Tennis Courts
    September 17, 2018 - Board approved Little Elm High School Ball Fields and Tennis Courts (Phase 1B Bond Project List)

    October 15, 2018 - Board approved Little Elm High School Ball Fields and Tennis Courts Budget

    June 17, 2019 - Board approved Little Elm High School Ball Fields Concourse and Concessions Budget 

    Stadium Scoreboard
    September 17, 2018 - Board approved Stadium Scoreboard (Phase 1B Bond Project List)

    November 26, 2018 - Board approved Stadium Scoreboard Budget 

    District-Wide Roofing
    September 17, 2018 - Board approved District-Wide Roofing (Phase 1B Bond Project List) 

    October 15, 2018 - Board approved District-Wide Roofing Budgets and Master Roofing Contract with Armko Industries

    December 17, 2018 - Board approved individual budgets for roofing projects at Zellars, Chavez ES, and Brent ES

    District-Wide HVAC
    September 17, 2018 - Board approved District-Wide HVAC project (Phase 1B Bond Project List) 

    May 20, 2019 - Board approved Energy Savings Performance Contract Budget and Agreement with Siemens Industry 

    New Buses
    September 17, 2018 - Board approved New Buses (Phase 1B Bond Project List) 

    February 18, 2019 - Board approved the purchase of eleven (11) 77 passenger buses and one (1) 47 passenger bus to replace leased Goldstar buses

    Stadium Improvements
    September 17, 2018 - Board approved Stadium Improvements (Phase 1B Bond Project List) 

    Technology Upgrades
    September 17, 2018 - Board approved Technology Upgrades (Phase 1B Bond Project List)

    Little Elm High School CTE Renovation
    September 17, 2018 - Board approved Little Elm High School CTE Renovation (Phase 1B Bond Project List) 

    May 20, 2019 - Board approved Little Elm High School CTE Renovation Budget

    Safety and Security Improvements
    September 17, 2018 - Board approved Safety and Security Improvements (Phase 1B Bond Project List) 

    Little Elm High School SPED Classroom Conversion
    May 20, 2019 - Board approved Little Elm High School SPED Classroom Conversion Proposal and Budget