Bond 2017 Board Approvals
Bond Election
January 23, 2017 - Board approved developing a Long-Range Facilities Planning Committee.
March 27, 2017 - Board approved Long-Range Facilities Planning Committee members.
August 7, 2017 - Board discussed Long-Range Faciliites Planning Committee recommendations.
August 10, 2017 - Board calls for $240 million Bond Election.
November 17, 2017 - Board canvassed Bond Election returns.
Bond Approvals
March 30, 2015 - Board approved architectural firms.
October 17, 2016 - Board approved reimbursement resolution.
December 18, 2017 - Board approved Construction delivery method.
December 18, 2017 - Board approved Local Emergency Planning Committee (tornado shelter).
May 21, 2018 - Board approved the Job Order Contract (JOC) renewal.
June 18, 2018 - Board approved Local Emergency Planning Committee.
October 15, 2018 - Board approved Job Order Contract results and recommendations.
March 22, 2021 - Board approved the contract for Long Range Bond Planning Services for Huckabee.
December 13, 2021 - Board approved the Job Order Contract (JOC) renewal.
Bond Issuance
February 19, 2018 - Board approved $150 million Bond issuance.
June 18, 2018 - Board approved $25 million Bond issuance.
May 20, 2019 - Board approved Order Authorizing Issuance of Bonds per 2017 Bond Election Passing Proposition B.
October 21, 2019 - Board approved $20 million Bond issuance.
October 19, 2020 - Board approved $25 million Bond issuance.
March 22, 2021 - Board approved $10 million Bond issuance.
June 20, 2022 - Board approved $5 million Bond issuance.
Land/Purchase Activity
October 19, 2017 - Board approved letter of intent for land with Tribute Partners.
March 26, 2018 - Board approved 26.123 acres land purchase in Tribute at The Colony.
August 20, 2018 - Board approved 12.332 acres land purchase in Little Elm - Valencia L.P.
August 20, 2018 - Board approved 1.177 acres land purchase in Little Elm - Hart Road.
August 26, 2018 - Board approved 35.24 acres land purchase in Oak Point - Wildridge L.L.P.
August 19, 2019 - Board approved 1.315 acres land purchase in Little Elm - Hart Road.
August 19, 2019 - Board approved land exchange of 16.376 acres located in the Town of Lakewood Village ETJ for 14.88 acres of Sam Hill Venture Property, also located in the Town of Lakewood Village.
October 18, 2021 - Board approved various utility easements at future school site in Valencia.
October 24, 2022 - Board approved a Land Use Agreement for a well easement on the future Lakewood Village school site.
November 28, 2022 - Board approved temporary construction easements for the residential developer who is building around the future school site.
Bond Projects
Brent & Chavez Vestibule
May 21, 2018 - Board approved JOC and budget for Security Vestibules at Chavez Elementary School and Brent Elementary School.
Walker Middle School
April 23, 2018 - Board names the two middle schools.
May 21, 2018 - Board approved construction manager for Walker Middle School.
October 15, 2018 - Board approved funding agreement for natural gas line extension at Walker Middle School and Transportation Facility.
December 17, 2018 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Walker Middle School.
August 19, 2019 - Board approved the Interlocal Agreement and Project Budget for LEISD's portion of the French Settlement Road replacement.
Strike Middle School
April 23, 2018 - Board names the two middle schools.
May 21, 2018 - Board approved construction manager for Strike Middle School.
December 17, 2018 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Strike Middle School.
February 18, 2019 - Board approved Project Budget and Construction Guaranteed Maximum Price (GMP) for Scotty's Lake Lane Off-Site Improvements.
June 15, 2020 - Board approved the budget to extend the sidewalk along Lebanon Road to the front of Strike Middle School.
July 27, 2020 - Board approved Change Order No. 1 to the Cadence McShane contract for the extension of sidewalks, crosswalks, and signage connecting the campus to the existing neighborhoods.
December 14, 2020 - Board approved Change Order No. 2 to the Cadence McShane contract for additional contingency funding to help pay for acceleration costs.
February 22, 2021 - Board approved the 6th amendment to the Real Estate Contract and Trail Maintenance Easement Agreement.
Little Elm High School Ball Fields and Tennis Courts
September 17, 2018 - Board approved Little Elm High School Ball Fields and Tennis Courts (Phase 1B Bond Project List).
October 15, 2018 - Board approved Little Elm High School Ball Fields and Tennis Courts Budget.
June 17, 2019 - Board approved Little Elm High School Ball Fields Concourse and Concessions Budget.
Stadium Scoreboard
September 17, 2018 - Board approved Stadium Scoreboard (Phase 1B Bond Project List).
November 26, 2018 - Board approved Stadium Scoreboard Budget.
District-Wide Roofing
September 17, 2018 - Board approved District-Wide Roofing (Phase 1B Bond Project List).
October 15, 2018 - Board approved District-Wide Roofing Budgets and Master Roofing Contract with Armko Industries.
December 17, 2018 - Board approved individual budgets for roofing projects at Zellars, Chavez ES, and Brent ES.
January 21, 2020 - Board approved Credit Change Order No. 1 to return a credit from Paragon Roofing along with unspent budget dollars to the program available balance.
District-Wide HVAC
September 17, 2018 - Board approved District-Wide HVAC project (Phase 1B Bond Project List).
May 20, 2019 - Board approved Energy Savings Performance Contract Budget and Agreement with Siemens Industry Phase I.
September 16, 2019 - Board approved the establishment of an Emergency HVAC Equipment Fund to replace failing/unrepairable equipment scheduled to be replaced in upcoming phases of the current bond program.
November 18, 2019 - Board approved Energy Savings Performance Contract Budget and Agreement with Siemens Industry Phase II.
June 28, 2021 - Board approved Energy Savings Performance Contract Budget and Agreement with Siemens Industry Phase III.
New Buses
September 17, 2018 - Board approved New Buses (Phase 1B Bond Project List).
February 18, 2019 - Board approved the purchase of eleven (11) 77 passenger buses and one (1) 47 passenger bus to replace leased Goldstar buses.
March 22, 2021 - Board approved the purchase of five (5) new buses.
May 17, 2021 - Board approved the proposal to upgrade the surveillance systems on district buses.
November 28, 2022 - Board approved the purchase of five (5) 77 passenger buses and one (1) 42 SPED passenger bus.
Stadium Improvements
September 17, 2018 - Board approved Stadium Improvements (Phase 1B Bond Project List).
September 16, 2019 - Board approved Athletic Complex Turf Replacement and Renovations project and budget.
April 20, 2020 - Board approved Stadium Track Replacement and Drainage renovation budget.
July 27, 2020 - Board approved Change Order No. 1 to the Stadium Track Replacement Project for corrective sub-grade work prior to placement of the new track surface.
Technology Upgrades
September 17, 2018 - Board approved Technology Upgrades (Phase 1B Bond Project List).
Little Elm High School CTE Renovation
September 17, 2018 - Board approved Little Elm High School CTE Renovation (Phase 1B Bond Project List).
May 20, 2019 - Board approved Little Elm High School CTE Renovation budget.
Safety and Security Improvements
September 17, 2018 - Board approved Safety and Security Improvements (Phase 1B Bond Project List).
July 29, 2019 - Board approved the proposal to provide and install ballistic glass safety film at Zone 1 areas of all existing campuses and both Middle Schools, when completed.
April 25, 2022 - Board approved District Security Camera Upgrades.
September 19, 2022 - Board approved the Security Fencing project at Little Elm High School.
Little Elm High School SPED Classroom Conversion
May 20, 2019 - Board approved Little Elm High School SPED Classroom Conversion proposal and budget.
April 19, 2021 - Board approved the Little Elm High School SPED Classroom and Office Conversion proposal and budget.
Little Elm High School Indoor Multi-Use Facility
March 23, 2020 - Board approved the professional services proposal from Corgan to design a new indoor multi-use facility on the LEHS campus.
December 14, 2020 - Board approved the Indoor Multi-Use Project budget which includes the GMP from Jackson Construction.
April 19, 2021 - Board approved Change Order #1 to add four divider curtains on the practice field portion of the indoor facility.
May 17, 2021 - Board approved the granting of the electric easement to support the new Indoor facility at LEHS.
July 24, 2023- Board approved the final change order to close project.
Lakeside Middle School Conversion to New Administration Complex
June 17, 2019 - Board approved Lobo Lane Conversion Study.
March 23, 2020 - Board approved the professional services proposal from HKS, Inc to design the conversion of Lakeside Middle School.
May 17, 2021 - Board approved the Lakeside Middle School Demolition budget.
May 26, 2021 - Board approved the master budget for the Conversion and Renovation of Lakeside Middle School.
November 15, 2021 - Board approved the name of the new administration facility: Little Elm ISD Administration Building.
January 24, 2022 - Board approved Change Order No. 1 to remove the metal building in front of Lakeside and replace it with parking.
February 28, 2022 - Board approved Change Order No. 2 to transfer $200,00.00 to Contingencies and Allowances with no increase in the Master Budget previously approved.
Prestwick
February 22, 2021 - Board approved the professional services proposal from Hidell and Associates for the underslab plumbing issues at Prestwick.
April 19, 2021 Board approved the procurement method for the Prestwick Elementary Subsurface Corrective Project.
May 17, 2021 - Board approved the CSP results recommendation and the Prestwick Elementary Subsurface Corrective and Renovations Budget.
Zellars Conversion
February 22, 2021 - Board approved the professional services proposal from HKS, Inc for the conversion of Zellars Learning Center to the new early childhood center.
November 15, 2021 - Board approved the name of the new facility: Herschel Zellars Early Childhood Learning Center.
June 20, 2022 - Board approved the GMP and master budget for the Zellars Early Childhood Learning Center renovation.
Miscellaneous Exterior Capital Improvements
March 23, 2020 - Board approved 2020 Roof Management Program.
February 22, 2021 - Board approved the project budget and scope to replace exterior wall panels and flashing at Little Elm High School.
April 19, 2021 - Board approved the sidewalk extension at Prestwick Elementary connecting Prestwick to a new subdivision.
August 23, 2021 - Board approved the replacement of heaved concrete egress sidewalks at all exits of Prestwick Elementary.
June 20, 2022 - Board approved the concrete drive replacement between the Lakeside Administration Building and Powell.
June 20, 2022 - Board approved the master budget and JOC costs to add a new entrance drive at Strike Middle School.
July 24, 2023- Board approved concrete slab for LEHS Food Trailer at Bistro.
Little Elm High School Welding Expansion Project
February 28, 2022 - Board approved the professional services proposal from Corgan Architects for the design and expansion of the LEHS Welding Lab.
April 25, 2022 - Board approved the GMP and master budget for the Welding Lab Expansion Project.
September 19, 2022 - Board approved the master budget for the Welding Lab Exhaust Systems Project
November 27, 2023 - Board approved the change order to close out the project.